Adjustable Triangle Rack Mounting System
Adjustable Triangle Rack mounting system is designed to meet the requirement of adjustable tilt angle of the bracket. This mounting system can be installed on both metal roof and flat concrete rooftop.
The main parts are Adjustable Triangle Rack, Rail, Rail Connector, Rail Clamp, Mid Clamp and End Clamp.
Specification:
| Brand | ZIYUAN |
| Material | AL6005/T5 & SUS304 |
| Surface Coating | Anodizing |
| Tilt Angle Range | 10~15°, 15~30° & 30~60° |
| Design Code | JIS C 8955 2017 |
| Standard | AS/NZS 1170 |
| Wind Speed | 60m/s |
| Snow Load | 1.4KN/m² |
| Warranty | 15 years |
| Service Life | 20 years |
Components (consider 2 panels mounting):

Warranty:
ZIYUAN Energy guarantees continuous power generation for 25 to 30 years.
The structure offered by Ziyuan Energy has 25 years service life and we offer warranty for 12 years.
The power output decreases by 2% in the first year and then by 0.45% each year from the second year through the 30th year.
This long-term durability allows clients to make sustained investments and plan stable business operations.
Installation Steps:
1. Unfold the pre-assembled Adjustable Triangle Rack, adjust the length of the side column according to the required optimal tilt angle, then lock the bolt tightly;
① If it is trapezoid metal roof, install the Adjustable Triangle Rack on the rooftop in the correct position as planned, drilling the screw into the roof beam below.
② If it is non trapezoidal metal rooftop, install the Clip Lock on the rooftop first then install the Adjustable Triangle Rack on the Clip Lock.
③ If it is flat concrete rooftop, install the Adjustable Triangle Rack on the rooftop directly with the expansion bolt, or install them on the cement block through embedded bolt.
2. Install the Rail on the Adjustable Triangle Rack with the Rail Clamp, lock the bolt tightly and make sure all Rails are in same level.
3. Install the solar panel on the Rails with the End Clamp and Mid Clamp, lock the bolt tightly.
Installation Guide
1. Installation of Adjustable Triangle Rack
1.1 Unfold the folded Adjustable Triangle Rack and assemble with M8*25 bolt. There is no need to lock the bolt too tightly now.

1.2 Install the Adjustable Triangle Rack on the cement roof or cement blocks (can use expansion bolt or embedded bolt of cement block). Make sure that the holes are in same level.

1.3 Adjust the length of adjustable pole as per actual need. Make sure the height of all Adjustable Triangle Rack are same. Lock all bolt tightly.

2. Installation of Rail
2.1 Rail connection (when Rail length is not enough)
Insert the Rail Connector into two Rail, use M8*10 bolt to fix well.

2.2 Install the Rail on the Adjustable Triangle Rack with Rail Clamp, fasten the bolt tightly.

3. Installation of Solar Panels
Install the Solar Panels on the Rail, use the End Clamp and Mid Clamp (with Earthing Plate) to fix and fasten the bolt tightly.

4. Installation of Grounding Lug
Install a Grounding Lug on the end of each Rail.

Product Package
We use durable and professional packaging to ensure that all solar mounting components arrive safely at your project site.

Why Choose Ziyuan Energy
1. Own Factory & Strict QC
Ziyuan has own factory with more than 100 skilled and experienced workers, the production line is strictly in accordance with high standards and attach great importance to quality control and inspection.

2. Experienced Engineer Team
The first-class production engineers, technicians and R & D team offer innovative design and reliable solution to customers based on more than 8 years of experiences.



3. Professional Service
Ziyuan has an excellent sales team, can quickly respond to customer inquiries and provide professional advice.