Field Installation Guide
RC Roof Mounting Structure Installation
A practical guide for concrete flat roofs, covering support layout, preassembled frames, AR50 rails, module clamps, grounding and final inspection.
A reliable RC roof mounting structure installation starts with an approved roof layout, correctly positioned concrete supports and a mounting system assembled in the right sequence. For the ZIYUAN system, that sequence is straightforward: install the bases, unfold and align the preassembled support frames, fit the back bracing, connect and position the AR50 rails, secure the PV modules, and complete the grounding work.
This guide is intended for EPC contractors, project engineers, installers and distributors working with photovoltaic arrays on reinforced-concrete flat roofs. It explains the standard assembly sequence shown in the ZIYUAN installation manual and demonstration video, while identifying the checks that still require project-specific structural and electrical design.
What Is an RC Roof Mounting Structure?
An RC roof mounting structure is a photovoltaic racking system designed for a reinforced-concrete flat roof. In some markets, particularly South Asia, the same roof type is commonly described as an RCC roof. The structure raises the PV modules above the roof surface, establishes the designed module tilt and transfers array loads into engineered concrete supports or approved roof attachment points.
ZIYUAN’s system uses anodized AL6005-T5 aluminum for the main mounting profiles. The assembly includes bases, preassembled beam-and-column frames, back braces, AR50 rails, rail connectors, rail clamps, end clamps, mid clamps, earthing plates and grounding lugs.
The system may be specified with precast supports, cast-in-place concrete supports or another engineered attachment arrangement. Do not assume that a concrete support automatically makes the installation non-penetrating or fully ballasted; the actual load path and waterproofing detail depend on the approved project design.
Before Installation
Do not place concrete supports or drill anchor holes until the roof layout and structural details have been approved. Confirm that the roof can carry the combined dead load of the PV modules, racking, concrete supports, electrical equipment and temporary installation loads.
- Review the roof structure and waterproofing condition.
- Match support dimensions and spacing to issued drawings.
- Confirm array orientation, tilt and roof-edge setbacks.
- Keep drains, joints and maintenance routes unobstructed.
- Match clamps to the module frame and clamping zones.
- Verify rail splices and thermal-expansion details.
- Confirm the project grounding and bonding arrangement.
- Check all parts for damage and missing hardware.
If roof penetrations are required, use the approved anchor and waterproofing detail. If the array relies on ballast, the support weight and friction assumptions must be confirmed by the project engineer for the actual roof zones and site conditions.
Concrete supports alone do not determine whether an installation is non-penetrating. For a broader explanation of roof attachment options, see our non-penetrating vs penetrating solar mounting guide (opens in a new tab), including how ballasted, attached and hybrid arrangements affect roof loading and waterproofing.
Tools and Components
Prepare the installation tools before lifting the mounting components onto the roof:
- String line or chalk line
- Tape measure and marking pen
- Drill or rotary hammer with approved bit
- M8 and M10 sockets
- 6 mm hex key
- Calibrated torque wrench
- Suitable socket wrench and rubber mallet
- Approved anti-seize compound, where specified
- Required PPE and fall-protection equipment
Avoid selecting the drill diameter solely from a general tool list. The hole diameter, drilling depth, cleaning method, embedment and installation torque must follow the instructions for the anchor approved for the project.
System Reference Details
| Component or reference | Manual detail | Installation relevance |
|---|---|---|
| Main structural material | Anodized aluminum alloy AL6005-T5 | Main profiles used for the RC roof mounting structure. |
| Illustrated concrete support | 600 × 350 × 165 mm; 120 mm anchor spacing | Manual reference detail; final dimensions and reinforcement require project structural verification. |
| Base 1 and Base 2 | M10 × 25 external-hex bolt or M10 × 100 expansion anchor | Connects the base to the engineered concrete support, subject to the approved fixing detail. |
| Beam-and-column kit | M8 × 55 column-to-base bolt | Preassembled support frame unfolded and aligned on site. |
| Back bracing | M8 × 50 bolt | Connects the brace to the rear column. |
| AR50 rail connector | 150 mm connector; 75 ± 10 mm insertion per rail | Joins adjacent AR50 rail sections. |
| Rail clamp | Installed at each specified rail-to-beam connection | Secures the AR50 rail to the inclined support beam. |
| End and mid clamps | Match the module frame and approved clamping zone | Secure the outer and adjacent module frames respectively. |
| Earthing plate and grounding lug | Install where required by the electrical design | Supports the project-specific bonding and grounding arrangement. |
This table is a quick reference to the illustrated system, not a replacement for the project bill of materials or issued construction drawings.
RC Roof Mounting Installation Video
Watch the RC roof mounting installation video on YouTube before starting the numbered steps below. The demonstration covers the preassembled beam kit, back bracing, AR50 rail connection, rail placement, end clamps and mid clamps.

- 00:00System overview
- 00:03Unfold the beam kit
- 00:10Fit the back bracing
- 00:16Join the AR50 rails
- 00:24Position the rails
- 00:32Install the end clamp
- 00:38Install the mid clamp
- 00:47Inspect the structure
RC Roof Mounting Structure Installation Steps
Follow the approved project drawings and complete the work in the sequence below. Keep the designated adjustment connections snug until the frame and rail alignment has been checked.
Set Out the Concrete Supports
Mark every support position from the approved array drawing. Establish control lines across the roof rather than measuring each support from the previous one; this reduces cumulative alignment errors along a long module row.
The concrete support illustrated in the ZIYUAN manual measures 600 mm × 350 mm × 165 mm, with the two internal anchors spaced 120 mm apart. These dimensions are reference details for the illustrated assembly, not a universal ballast or foundation design. The structural engineer must confirm the concrete dimensions, reinforcement, concrete grade, anchor arrangement and required resistance for the actual project.
Position the supports on the marked grid and recheck row centres, diagonals and clearances. Do not obstruct roof drains, expansion joints, access routes or equipment service zones.
Fix the Bases
Position Base 1 and Base 2 on the concrete supports in the orientation shown on the project drawing. Depending on the approved connection detail, secure the base with an M10 × 25 external-hex bolt connected to the specified embedded fixing, or use the approved M10 × 100 expansion anchor.
Keep each base square to the array control line. Before tightening, confirm that the front and rear bases are correctly oriented and that the support frame will open in the required tilt direction.
When expansion anchors are used, follow the anchor manufacturer’s requirements for drill diameter, drilling depth, hole cleaning, edge distance, embedment and installation torque. Do not replace the approved anchor with another product simply because it fits through the base hole.
Unfold the Beam-and-Column Frames
Lift each preassembled beam-and-column kit onto its base pair and unfold it carefully. Connect the columns to the bases using the supplied M8 × 55 bolts.
Keep the designated adjustment connections snug rather than fully torqued at this stage. The frames must retain enough movement for row alignment, but they must not be left unstable. Use temporary support if required and keep hands clear of folding joints and pinch points.
The preassembled design reduces the number of separate members that must be positioned on the roof. It does not remove the need to check every connection before final tightening.
Align and Level the Frames
Install the remaining support frames in the row. Use a string line, laser or suitable leveling instrument to check the upper surfaces of the inclined beams. They must form a consistent plane before the rails are installed.
- Position every frame on the correct centre line.
- Match support spacing to the issued layout.
- Align columns and inclined beams as required by the design.
- Keep corresponding beams across the row on the same plane.
Correct the alignment now rather than forcing rails or module clamps to pull a distorted structure into position. Once the row is aligned, tighten the base and frame connections to the torque values specified for the project.
Install the Back Bracing
Connect the back brace to the rear column using the supplied M8 × 50 bolt. Install the washers and nuts in the orientation shown in the assembly drawing, then tighten the connection evenly after the frame alignment has been confirmed.
Install the back bracing in the exact single-braced or cross-braced orientation shown in the approved assembly drawing. Do not omit a brace, change its fixing point, or modify the member to avoid an obstruction. If a brace conflicts with roof equipment or another structural component, stop work in that area and request an engineering review.
Join the AR50 Rails
Where a rail run requires more than one section, use the connector specified for the AR50 profile. In the ZIYUAN installation manual, the illustrated connector is 150 mm long and is inserted 75 ± 10 mm into each adjoining rail section.
Insert the connector into the first rail, slide the adjoining rail over the exposed half and align both rail faces. Centre the connector across the joint and tighten its two bolts evenly. If the approved rail layout includes an expansion gap or a different splice detail, follow that project drawing rather than closing the rail ends automatically.
A stepped or twisted rail joint can interfere with module placement and introduce unwanted stress into the module frame. Check alignment across the splice before final tightening.
Secure the Rails to the Beams
Place the AR50 rails across the aligned support beams in the positions shown on the array drawing. Fit a rail clamp at each specified rail-to-beam intersection and tighten it enough to hold the rail while final spacing and alignment are checked.
Set the rail spacing according to the PV module manufacturer’s approved clamping zones. Confirm that both rail lines are parallel and that the rail grid is square to the support frames. After completing the checks, tighten the rail clamps to the project torque schedule.
Install the First PV Module
Lift the first module onto the rails using the handling method required by the module manufacturer. Keep the module supported until the end clamps are correctly engaged.
Insert the end clamps at the outside edge of the row. Position each clamp within the module manufacturer’s approved clamping zone, seat it squarely against the module frame and tighten it to the specified torque. The clamp must not contact the glass, backsheet, junction box or cable leads.
Fit the Mid Clamps and Earthing Plates
Place the next module on the rails and maintain the required module gap. Insert a mid clamp between the adjacent module frames. Where the approved bonding design calls for an earthing plate, install it in the specified position and orientation.
Tighten the mid clamp evenly while checking that it captures both module frames correctly. Continue along the row and verify alignment every few modules rather than waiting until the row is complete.
Do not assume that every earthing plate is compatible with every module frame or that mechanical contact alone establishes the required electrical bond. Compatibility, bonding continuity and the permitted current path must be confirmed for the selected module and mounting system.
Install the Grounding Lugs
Install a grounding lug at the end of each rail, or at the locations specified in the electrical drawings. Prepare and terminate the grounding conductor using the approved hardware, conductor size and installation method, then connect it to the project grounding system.
Do not treat the equipment grounding bond as a substitute for a dedicated lightning-protection system unless this arrangement is specifically defined in the approved project electrical design. Complete the required bonding and continuity tests before electrical commissioning.
Complete the Final Inspection
Inspect the structure row by row before releasing the array for electrical commissioning. Verify that:
- Supports and bases match the approved layout.
- Anchors and waterproofing details are complete.
- Frames are aligned, braced and undamaged.
- Rail splices and expansion details match the plan.
- Module clamps sit in approved clamping zones.
- Fasteners are tightened and marked where required.
- Grounding parts are installed in specified locations.
- Cables avoid sharp edges and standing water.
- Drains and maintenance routes remain open.
- Loose hardware and debris have been removed.
Prevent Stainless-Steel Fastener Galling
Stainless-steel fasteners can seize when their threads are contaminated, misaligned, overtightened or driven too quickly. On site, this is commonly described as thread galling or cold welding.
Recommended Practice
- Keep threads clean and free from dust, grit and swarf.
- Start nuts and bolts by hand.
- Keep the fastener aligned with the thread axis.
- Use approved anti-seize where specified.
- Tighten with smooth, controlled force.
- Use a calibrated torque wrench for final tightening.
Stop and Replace
If a fastener begins to bind, stop rather than forcing it further. Replace damaged hardware and inspect the mating thread before continuing.
Use the project torque schedule rather than a generic table. Lubrication changes the relationship between tightening torque and bolt tension.
Common Installation Mistakes
Treating the Block Drawing as Universal
The illustrated support size does not replace project-specific checks for roof capacity, wind conditions, reinforcement and attachment design.
Tightening Frames Too Early
Locking the connections before row alignment can leave the support beams on different planes.
Ignoring Module Clamping Zones
Confirm clamp position and torque in the PV module manufacturer’s installation instructions.
Assuming Every Support Is Ballast
A concrete support may act as ballast, an anchor foundation or part of a hybrid engineered attachment.
Closing Every Rail Joint
Some long rail runs require a designed thermal-expansion detail. Follow the issued rail plan.
Driving Stainless Fasteners Too Quickly
High-speed tightening raises the risk of thread galling. Align correctly and finish with controlled torque.
Why Use a Preassembled Aluminum System?
For commercial and industrial rooftop projects, installation planning must account for roof loading, handling time and repeatable assembly. ZIYUAN’s preassembled beam-and-column units reduce the number of separate frame members that crews must identify and connect on the roof.
The rail-based arrangement also allows installers to check the support plane and rail spacing before modules are clamped. The bill of materials is built around repeatable system components: bases, support frames, braces, AR50 rails, rail connectors, rail clamps, module clamps and grounding hardware.
For a project-specific proposal, provide the installation address, roof drawings, building height, PV module datasheet, array arrangement, preferred tilt angle, design wind and snow loads, allowable roof load, concrete details, fixing preference and applicable design standard.
Frequently Asked Questions
What is an RC roof mounting structure?
An RC roof mounting structure is a PV racking system designed for a reinforced-concrete flat roof. It supports the modules at the designed tilt and transfers array loads into engineered concrete supports, anchors or another approved attachment arrangement.
Is an RC roof the same as an RCC roof?
In rooftop solar terminology, RC and RCC generally refer to reinforced-concrete construction. “RCC roof” is commonly used in South Asian markets, while “RC roof” is frequently used in engineering documents and product names.
Can the system be installed without penetrating the roof?
A concrete-roof array may be ballasted, anchored or designed as a hybrid system. Whether penetrations can be avoided depends on wind uplift, roof capacity, waterproofing, array geometry and applicable project requirements.
What material is used for the ZIYUAN structure?
The main mounting profiles in the illustrated system are made from anodized AL6005-T5 aluminum. Confirm the supplied fasteners, clamps, grounding components and anchors in the project bill of materials.
What concrete support size is required?
The ZIYUAN manual illustrates a 600 × 350 × 165 mm concrete support with 120 mm anchor spacing. The actual dimensions, reinforcement and quantity must be confirmed through project-specific structural design.
How are the AR50 rails connected?
The illustrated AR50 rail joint uses a 150 mm internal connector inserted 75 ± 10 mm into each adjoining rail. Any required expansion gap or alternative splice arrangement must follow the issued rail layout.
What is the difference between an end clamp and a mid clamp?
An end clamp secures the outside frame of the first or last module in a row. A mid clamp sits between two adjacent modules and secures both frames to the rail.
Where should PV module clamps be positioned?
Place end and mid clamps within the clamping zones specified by the PV module manufacturer. Do not select clamp positions only from visual appearance or rail convenience.
How is the array grounded?
The mounting system includes earthing plates and grounding lugs for use where required by the approved bonding and grounding design. Their quantity, location, conductor connection and verification method must follow the project electrical drawings and applicable requirements.
What information is needed for a mounting proposal?
Provide the project location, roof plan, building height, module model and dimensions, array layout, tilt angle, concrete-roof details, preferred fixing method, design wind and snow loads, applicable standard and delivery schedule.